What is the role of the RWIC before beginning work when a main track is removed from service?

Study for the NORAC Dispatcher Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The role of the RWIC (Railroad Work Inspection Coordinator) before beginning work when a main track is removed from service is crucial for ensuring safety and proper procedure adherence. Confirming with the dispatcher that the "Track Out of Service" (TOL) indication is displayed is essential because it verifies that the main track has indeed been officially designated as out of service for the duration of the work. This step is critical to prevent any potential conflicts with train movements and to ensure that all personnel involved in the work are safeguarded.

The TOL display serves as an important communication tool between the RWIC and the dispatcher, solidifying the understanding that nobody should be operating trains on that specific track section while work is being conducted. Thus, this confirmation ensures that all safety protocols have been followed and minimizes the risk of accidents.

Other choices, while they may seem relevant, do not directly pertain to the critical preparatory action of confirming the TOL status before work begins. For example, ensuring no workers are in the area is indeed a safety consideration, but it becomes necessary only after confirming that the track is officially out of service. Checking weather conditions and testing communication systems are also important tasks, but they do not hold the same immediate significance in the context of

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy