Which information must be included when granting permission to foul the track?

Study for the NORAC Dispatcher Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

When granting permission to foul the track, it is essential to include the Four T's: Title, Track designation, Track limits, and Time Limits. This information is vital for ensuring the safety and clarity of operations on the railway.

The Title indicates who is granting the permission, ensuring accountability. The Track designation specifies which track is affected, allowing all parties to understand the exact location involved. Track limits define the specific areas within which the foul is applicable, providing clear bounds to prevent any confusion about where the restrictions apply. Finally, Time Limits establish the timeframe during which the foul is in effect, allowing for timely communication and operational planning.

This comprehensive set of information helps to mitigate risks and ensures that all involved personnel are aware of the circumstances surrounding the permission granted to foul the track, thereby maintaining safety protocols within railway operations.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy